Introduction: Beijing subway line 14 includes four stations and approximately 2.8 km of tunnels between the Dongfengbeiqiao and Jingshunlu areas of the city. Due to the surface and underground space limitations of this section, a double-track running tunnel instead of two single-track running tunnels was adopted to connect the two stations. The double-track tunnels were excavated by a 10.22 m diameter earth pressure balance (EPB) shield. It was the first time that an EPB shield more than 10 m in diameter was used in Beijing subway construction.
Case Description: The shield, which passes underneath densely built-up areas of the city and is equipped with a spoke-type cutterhead, with balance between the ground pressure and the earth chamber pressure at the tunnel face, is of great importance. Referring to experiences gained in the EPB shield tunneling, attention was paid to the function of soil conditioning and simultaneous backfilling grouting of the shield, and some special designs were considered in manufacturing the machine.
Discussion And Evaluation: In addition to the agitating rods welded to the cutterhead, two independently driven agitators were added to fully mix everything in the earth chamber. Independent pipelines were arranged for injecting different conditioning agents. Indoor tests in combination with field tests were conducted to find suitable additives and injection ratios of the additives, and determine the mix ratio of the two-component grout for simultaneous backfilling grouting. A scheme was employed for simultaneously injecting the bentonite slurry at 8% concentration and the foam liquid at 5% concentration to condition the excavated soil. The cement-sodium silicate grout was adopted to fill the tail void and the injection volume per ring was 14.1-15.3 m.
Conclusions: The performance of the shield and evaluation of the corresponding tunneling technologies are introduced in terms of the shield tunneling induced ground surface settlements. The success of the project is of great significance to Beijing subway construction and underground space utilization. The findings serve as a useful reference for similar projects.
Download full-text PDF |
Source |
---|---|
http://www.ncbi.nlm.nih.gov/pmc/articles/PMC5121113 | PMC |
http://dx.doi.org/10.1186/s40064-016-3672-5 | DOI Listing |
Sci Rep
December 2024
School of Civil Engineering and Architecture, East China Jiaotong University, Nanchang, 330013, Jiangxi, People's Republic of China.
Compared with simple formations, EPB (earth pressure balance) shield tunnelling in composite formations encounters severe problems with muck conditioning and require improved muck conditioning technology to fulfil expectations for continuous and efficient excavation. In the Nanchang Metro Line 4 Project, a water-rich sand-argillaceous siltstone composite formation is encountered. With a high moisture content and complex composite formation ratio, it is quite difficult to determine the optimum muck conditioning scheme, and thus, muck spewing accidents frequently occur during the tunnelling process.
View Article and Find Full Text PDFPLoS One
September 2024
Heilongjiang North Tools Co., Ltd, Mudanjiang, China.
The excavation of Earth Pressure Balance (EPB) shield can be divided into two distinct stages, i.e. advancing and lining installation.
View Article and Find Full Text PDFEnviron Sci Pollut Res Int
January 2024
China Railway 18Th Bureau Group First Engineering Co, Ltd, Baoding, China.
Earth pressure balance (EPB) shield is increasingly employed in metro tunnel construction, and causes a series of environmental, safety, and resource waste problems due to the disposal of a considerable amount of muck. In situ recycling of EPB shield muck is an effective solution, whereas the foam is generated by residual foaming agents used as the muck conditioning material during tunnelling, which often adsorbs clay particles and overflows the flocculation tank. To achieve defoaming and antifoaming during the reuse of muck, this study prepared novel eco-friendly silicone oil-polyether defoamers by condensation, compounding, and shear emulsification.
View Article and Find Full Text PDFData Brief
December 2022
MOE Key Laboratory of Intelligent Manufacturing Technology, Department of Civil and Environmental Engineering, College of Engineering, Shantou University, Shantou, Guangdong 515063, China.
This data presented in this article pertain to measured data obtained from earth pressure balance (EPB) shield tunelling of Guangzhou-Foshan intercity railway project. The measured data consists of geological characteristics and the main shield parameters in each lining ring during shield tunnelling. The distribution of raw data was displayed, and the geological characteristics via field record were compared to the prediction results of improved stacking method.
View Article and Find Full Text PDFMethodsX
October 2022
MOE Key Laboratory of Intelligent Manufacturing Technology, Department of Civil and Environmental Engineering, College of Engineering, Shantou University, Shantou, Guangdong, 515063, China.
Geological characteristic (GC) is one of the most essential factors influencing setting earth pressure balance (EPB) shield parameters and cutterhead wear. Identification of GC has crucial significance to shield tunnelling efficiency and safety. Stacking classification algorithm (SCA) is widely applied in engineering with the identification and classification.
View Article and Find Full Text PDFEnter search terms and have AI summaries delivered each week - change queries or unsubscribe any time!