Proc Natl Acad Sci U S A
October 2024
As countries pursue decarbonization goals, the rapid expansion of transmission capacity for renewable energy (RE) integration poses a significant challenge due to hurdles such as permitting and cost allocation. However, we find that large-scale reconductoring with advanced composite-core conductors can cost-effectively double transmission capacity within existing right-of-way, with limited additional permitting. This strategy unlocks a high availability of increasingly economically viable RE resources in close proximity to the existing network.